WINDHAM - A seemingly mundane Windham planning board meeting has ramped up already escalating resistance to the ongoing review of a potential new hotel at the Windham Mountain Club.
Town planners, on November 5, spent an hour and more painstakingly plodding through a plethora of proposed changes to the ski center’s previously approved development Master Plan.
That plan was conditionally passed, last year, involving 60 townhouses on ski center lands. The WMC now wants to replace a number of those residential units with a 26-room luxury hotel and four villas.
A new environmental impact study (SEQRA) was conducted over the past few months and okayed by planners in late October, determining there would be no deleterious effects (a negative declaration).
Controversy and drama have arisen, however, as a group of local hoteliers have asked for a pause in the overall approval process, challenging the validity of the planning board amid multiple member recusals.
And fresh fuel has been added to that growing furor focusing on a visual regarding one of the recused members during the otherwise ho-hum November 5 planning session.
Three planners with work or membership links to the WMC have excused themselves from the discussions and any decision-making, wanting to remove any appearance of a conflict of interest.
The board has legally proceeded with only three members but the group of local hoteliers, led by Wylder Windham owner John Flannigan, are questioning the rightness of the process.
And joined by State Senator Michelle Hinchey, they have voiced concern about the status of a fourth member, chairwoman Lisa Jaeger, while requesting that the town board step in.
Hinchey, in an October 22 letter to the planning and town boards stated, “I write today with a deep love of Windham, and that love is driving a genuine concern for its long term stability and overall future.
“When my now-husband and I decided to get married…we chose Windham as the backdrop and got married at a local hotel (Wylder Windham) in 2025,” she wrote.
“I have strong concerns about the proposed change to the Windham Mountain Club’s plan and the process surrounding its consideration,” Hinchey continued.
“The fact that only two members of the five-member planning board, along with an alternate, are making such a consequential decision about the town’s future is deeply concerning and raises serious questions about the legitimacy of the process and fair consideration,” Hinchey wrote.
“These concerns are further heightened by the fact that [Jaeger] also chairs the [Windham] Chamber of Commerce, whose organization is financially tied to the applicant,” Hinchey wrote.
The ski center, for many years, has contributed to the success of the annual Autumn Affair, a street festival sponsored by the Chamber.
And the current WMC president and hotel applicant, Kristen Leach, serves on the Chamber board of directors with Jaeger.
If the fourth recusal occurred, it would reduce the planning board to two members, likely halting the review process and potentially nullifying all actions that have thus far taken place regarding the hotel application.
Jaeger has issued a statement declaring that her volunteer role with the Chamber is “separate and distinct” from her planning post, each fully transparent with no conflict of interest inherent.
And the planning board’s special counsel, Allyson Phillips, in an October 15 memo, stated Jaeger, “is not party to any agreements with the applicant whereby she may receive a payment or other benefit that is contingent or dependent on the planning board granting a favorable approval.”
Town supervisor Thomas Hoyt and town board members have made their thinking clear, that the planing board is operating independent of the town board, with oversight and conflict of interest matters properly unfolding.
******
Nevertheless, in her October 22 letter, Hinchey wrote, “I urge the town to reconsider its previous determination for a negative (SEQRA) declaration in light of this project’s potentially massive impact on the community.
“Further, even if one is not legally required, a feasibility study is the right step to take in order to do necessary due diligence, provide transparency and to understand the long term impacts to the town itself,” she wrote.
Leach, in a November 4 response to the Senator, stated, in part, “Senator Hinchey’s suggestion is based on a ludicrous false premise and by her
own admission is not a legitimate and legally supported requirement.
“The town of Windham has +/-372 hotel rooms available for booking and another +/-489 AirBnb or VRBO rental,” Leach wrote.
“The addition of 30 luxury hotel rooms is insignificant in relation to what the market currently comprises,” Leach wrote
“The Senator’s suggestion ignores the overwhelming positive economic effects of WMC activities related to the recent applications before the Planning Board,” Leach wrote.
“As the [SEQRA] Determination has been made, the application is complete, and the public hearing has been closed,” Leach wrote.
“We respectfully request the Planning Board move forward with its
review of the request for Amendment to Preliminary Plat and Site Plan,” Leach wrote.
*******
Some intrigue has arisen. Hinchey, in an October 15 letter to the two boards, referenced a “feasibility study,” writing, “I join the calls of local businesses and residents asking to see the feasibility study for this project.
“The public has a right to see this document, and the longer it is shrouded in secrecy, the larger the appearance of impropriety,” she wrote.
Subsequent interviews by the Mountain Eagle with various officials tied directly to the project revealed the feasibility study does not exist.
Hinchey, in her October 22 letter, stepped back, stating that the “previous version of this letter requested the release of a feasibility study as I was under the impression one had been conducted.
While not detailing the reason for her impression, Hinchey wrote, “I apologize for that incorrect information as I have not seen a feasibility study in the public record.”
The lack of that study, however, “is equally as troubling to me,” the Senator wrote. “I would urge [the planning and town boards] to step in now, stop this proposal from moving forward and provide residents with the transparency they deserve.”
******
In a memo to planners prior to their November 5 meeting, project consultant and senior planner Adam Yagelski wrote, “we have drafted this memo and the accompanying comparison table in an effort to aid Planning Board deliberations with respect to the applicable subdivision and site plan review criteria and design standards.
“This memo is structured based on the findings, relative to the review criteria set forth adopted by the Board as stated in the Board’s April 3, 2025 conditional preliminary plat and site plan approval resolution,” he wrote.
“For each subdivision and site plan criterion, the enclosed table recites or summarizes those findings, and also summarizes proposed modifications, and analyzes these modifications in the context of the criteria,” he wrote.
“Similar to the Board’s review approach to the initial Windham Resort Master Plan application for site plan and subdivision approval, in the included table, below, the subdivision and site plan law criteria
in the attached are grouped where there is substantive overlap.
“For example, site plan circulation criteria (Art. IV Sect. 4.010(B)) and subdivision law road design standards (Art. IV General Requirements and Design Standards, Section 2 and 3) are grouped,” Yagelski wrote.
“Finally, we have enclosed copies of the previously approved site plan and renderings and proposed site plan and renderings for the Board’s ease of use,” Yagelski wrote.
Flannigan and Albergo Allegria hotel owner, Marianna Radelich-Leman, who have signed the letter asking for the WMC pause, were at the November 5 planning meeting, recording the proceedings.
They entailed tedious, albeit necessary line-by-line comparisons to what planners had earlier approved and are now giving a second look.
One recused planner was sitting in the audience next to Leach who is a regular attendee. The planner returned to the head table after the conversations about the WMC ended.
Flannigan, in a November 9 letter to Supervisor Hoyt, took strong exception to the optics, stating, “I am writing regarding yet another troubling incident involving the Windham Mountain Club hotel application.
“Ray Curtis, who formally recused himself from the hotel application due to conflicts with Windham Mountain Club, was observed seated directly beside WMC President Kristin Leach.”
Flannigan stated Curtis was, “speaking and whispering with [Leach] while the applicant's consultants were presenting to the Planning Board.
“We have expressly rejected and challenged Ms. Phillips's prior conclusions concerning the conflicts in this matter,” he wrote.
“I call on you to initiate an independent review of the conflicts and recusals involving this application and reconsider whether the proceedings should begin anew before an appropriately constituted Planning Board,” he wrote.
“The town needs to stop dismissing these concerns,” Flannigan wrote to Hoyt. “I expect a substantive written response addressing each of these issues without delay.”
Hoyt, when asked about the matter by a resident during a town council meeting on November 10, said, “we’ve been looking into a lot of issues brought to our attention.
“Many of the issues are [someone’s] opinion. We are not turning a blind eye to any concerns of residents. We are all doing our due diligence to make sure everything is conducted properly,” Hoyt said.
A 62-day deadline for issuing a final WMC decision began on October 15. The deadline can be extended if agreed upon by all parties.
The next planning board gathering is slated for November 19 when officials are expected to openly continue their review.
Pictured: Curtis and Leach at the meeting sent to us by John Flannigan